24 June 2020 NIWP Updates – Greenhithe Road

Dear Greenhithe residents, Please find Northern Interceptor Wastewater Pipe Project updates on road works on the Greenhithe Road below: We (Fletcher) had originally planned to reseal the intersection of Wainoni Heights and Greenhithe Road on 25 June, but this has now been rescheduled for Saturday 27 June, commencing at approximately 7.30am. These works are weather [...]

By | June 24th, 2020|Community Info, Infrastructure|0 Comments

Project Updates June 2020 – Rahui Reserve

Dear Greenhithe residents, Please find updates on the Rahui Reserve section of Northern Interceptor Wastewater Pipe Project from the contractor below: The current Traffic Management Plan has been extended until the end of July 2020. At the completion of the chamber works, the road closure will be uplifted, and the road will be open to through [...]

By | June 10th, 2020|Community Info, Infrastructure|0 Comments

Road Work Notice (April 2020) – Austin Road Resurface, Greenhithe

Auckland Transport and its designated contractor Downer NZ wish to notify you that we will soon be undertaking resurfacing works in your street. This work is necessary to ensure the safety of traffic and to sustain the serviceability and appearance of the road.  This work is authorised by AT under Covid-19 conditions level 3. Please ensure [...]

By | April 30th, 2020|Infrastructure|0 Comments

Project Update (April 2020) – Northern Interceptor Wastewater Pipe construction on Greenhithe Rd.

Dear Neighbours, please find project updates from Stakeholder Manager Claire below (you may download original letter at the end) Greenhithe Road Works Post lifting of COVID-19 Level 4 restriction. We wish to update you on works associated with Watercare’s Northern Interceptor Project, Greenhithe Road works. Due to the delay in our works caused by COVID-19 [...]

By | April 24th, 2020|Community Info, Infrastructure|0 Comments

Road Work Notice (Jan 2020) – Austin Road, Greenhithe

The road works on Austin Road is completing next week (project period: 3 January - 5 February 2020), the contractor would like to let us know what had been done and what to expect in the last week. Read their letter below (a link for pdf copy at the end of this article): Auckland Transport [...]

By | January 30th, 2020|Infrastructure|2 Comments

Project Update (Nov 2019) – Northern Interceptor Wastewater Pipe construction

New updates (links to download the original communication letters from the constructor can be found at the end of this post): - Greenhithe Road On one evening between 26 to 28 November, we (Fletcher Construction) will bring a crane into site to lift a large concrete chamber into the ground adjacent to Sunnyview Road. During [...]

By | November 21st, 2019|Community Info, Infrastructure|0 Comments

Project Update (Oct 2019) – Northern Interceptor Wastewater Pipe construction

New updates (a link to download the original communication letter from the constructor can be found at the end of this post): On Greenhithe Road Stop-go traffic management will be in place during the day, with temporary traffic lights in operation at night. There will be no street parking adjacent to the work site. Working hours will [...]

By | October 29th, 2019|Community Info, Infrastructure|0 Comments

Change of Traffic Rules – Greenhithe Road (Northern Interceptor Wastewater Pipe Project

Commencing on Thursday 8 August, the Greenhithe shops will open up a second driveway entrance to the carpark. This will then turn the carpark into a one way in and one way out. Please be aware that you may turn in to the car park from both directions but on leaving you may only turn [...]

By | August 7th, 2019|Infrastructure|0 Comments

Work Notice – Greenhithe Bridge

As part of Watercare’s Northern Interceptor Project, we will be undertaking an inspection of the underside of Greenhithe Bridge.  Works will commence on the 11 August from 9.00pm to 5.00am Sunday to Thursday  for five consecutive nights for approximately five to six weeks.  Works are weather dependant. The underbridge unit will access the shared path off [...]

By | August 2nd, 2019|Infrastructure|0 Comments

Project Update – Northern Interceptor Wastewater Pipe construction – Rahui Reserve

The toilet block located at Rahui Reserve will be demolished to make way for Horizontal Directional Drilling (HDD) site establishment.After the toilet block is removed, HDD site establishment will begin on Rahui Reserve.At the completion of the drilling works, a replacement toilet block will be constructed.Hours of work are 7am – 6pm Monday to Sunday [...]

By | July 30th, 2019|Infrastructure|0 Comments